Lead Time Update
Update Feb 8th -
BP - 19 Weeks
H20 - 18 Weeks
H32 - 19 Weeks
All molding lines are now seeing very large demand. Forecasts are indicating that we will continue to see this demand until the end of 2024. A lot can change in that time but we continue to ramp up our operation to bring the leads times down.
We are replacing one of our BP's in March with a new Sinto 1620 which will provide faster cycle time and better quality. This will cause a roughly 2 week period of reduced production while installation takes place.
We're continuing to on-board and train new employees as fast as possible but retention has proven to be tough. We are now looking toward non-traditional options to increase our workforce as well.
Thank you for your understanding and patience as we adapt to this rapidly changing manufacturing environment.
Jeff Herdman
General Manager